POLICY: FERC denies PJM's IRAS proposal, accepts Large Load Registry

This story was originally published exclusively for NPM subscribers.

New Project Media (NPM) is a leading market intelligence & data platform covering US, European & APAC power, renewables & data markets and serving the development, finance, advisory & corporate community. Click here to schedule a demo or learn more.

  • FERC accepted PJM’s proposed definition and registry of large loads
  • Requires LSEs to report information meant to help PJM assess transmission-system impacts
  • PJM must file compliance details within 30 days

The Federal Energy Regulatory Commission (FERC) issued an order denying PJM’s Interim Resource Adequacy Service (IRAS) proposal but accepting the proposed Large Load Registry.

PJM proposed IRAS along with the suspended Reliability Backstop Procurement (RBP) in August to address the forecasted 6.8 GW shortfall from the capacity auction for the 2028/29 delivery year. The increase in energy demand is data center driven, according to PJM in its filings.

FERC previously suspended the RBP auction until February pending changes to the cost allocation provision, transmission owner exit rules and load-serving entity (LSE) collateral requirements.

The order accepted PJM’s proposed definition of Large Load establishing a cumulative peak threshold of 50 MW. FERC denied arguments from parties who had filed comments protesting this threshold or targeting only data centers.

FERC also accepted the proposed Large Load Registry that will require load-serving entities (LSEs) to submit information to PJM about the Large Loads they serve. The registry will provide relevant information for PJM to address the operational impacts of Large Loads on the transmission system, said the commission in the order.

However, the commission rejected PJM’s contested IRAS framework that proposed curtailments on Large Loads during resource adequacy drops and a Bring Your Own New Capacity (BYONC) provision.

Issues with IRAS

Stakeholders had filed comments alleging PJM was shifting the blame to large loads rather than internal issues and interconnection delays. Some parties argued that IRAS’s attempts to reach retail customers fell between state and federal jurisdictions, making it vulnerable to legal challenges.

FERC found that IRAS went beyond the commission’s authority due to the jurisdictional overreach and found that PJM had not provided sufficient evidence that the curtailment provision would not be unduly discriminatory.

The proposal was a signal to large loads to buy new capacity, according to Grant Glazer, senior manager of regulatory and market affairs at MN8 Energy.

“There’s a question of who gets first dibs for the resource adequacy that exists in the system,” said Glazer in an interview with NPM. “And IRAS is PJM’s answer to that question. The goal is we need new capacity or else we need a plan for what happens when we are short capacity.”

MN8 Energy is a developer for 23 solar, two storage and one solar-plus-storage projects currently in PJM’s interconnection queue, according to NPM data.

“MN8 is interested in the RBP because we see it as a driver for new demand and a way to encourage buyers to contract bilaterally with resources, IRAS does the same thing,” said Glazer.

PJM proposed IRAS to address concerns that existing customers were bearing the consequences of an imbalance between large load demands and available new generation, according to Jeff Shields, spokesperson for PJM.

Shields told NPM that FERC’s acceptance of the definition and registry for large loads is a step forward in its goal to maintain reliability and affordability of the grid by requiring data centers and other large loads to fulfill their commitments through the Ratepayer Protection Pledge.

“We are reviewing the commission’s order with an eye toward how we can fulfill FERC’s requirements while recognizing the responsibilities FERC indicated belong to the states and honoring the concept that existing electricity customers should not be unfairly burdened by new, energy intensive customers in the form of higher costs or decreased reliability,” said Shields.

The accepted definition and registry took effect Oct. 12, and PJM must submit a compliance filing limited to those provisions within 30 days. The order also offered guidance on refiling a modified IRAS proposal.